See Construction Portfolio page for more photos.
See Construction Portfolio page for more photos.
Bricks can now be seen starting on the east elevation of the library. In addition, drywall is almost completely installed in the ...
The new library and shared space is now completely enclosed. Most of the steel wall studs are in place. The ...
Steel wall studs are being cut and placed in tracks throughout the new library.
On the first floor of the new library, workers are busy roughing-in the electrical wiring, while on the second floor, ...
Click here to see what else is going on at the new library site.
Workers are shown here pouring the concrete slab for the library’s upper level.
Workers have started constructing the first set of stairs in the library. Preparation is being made for the second floor concrete to ...
Here is a view of the shared space from Washington Street.
Here is an aerial view of the new library site.
Galvanized steel studs can now be seen outlining what will be a parapet wall bordering part of the shared space roof.
Here are the floor plans of the new building.
The FDL director, Amy Falasz-Peterson, had the opportunity to take photos from a scissor lift today. Her other photos can be viewed by ...
Steel columns have been erected in the library space.
A steel beam is being added to the lobby area between the shared space and the library. This photo also ...
The concrete for the second library slab was poured this morning. More photos of this and other onsite activity can ...
Workers can be seen here welding the metal roof decking to the steel beneath it in the shared space. The ...
The concrete for the first half of the library’s concrete slab was poured today! Workers continue to work on the steel ...
More trusses are being welded in the shared space while other workers are waterproofing the elevator shaft. Visit our Construction Portfolio page ...
Pictured here is the steel structure framing the shared space as seen from Washington street. To view more photos, click on the ...
The steel frame for the shared space is starting to take shape as seen in this photo taken from Richland Street. ...
One worker is seen here stabilizing a newly erected steel column while another bolts it to its base-plate in the shared space.
The concrete slab for the shared space has been poured. A worker is shown here cutting control joints into the ...
Wire mesh panels are in place for the reinforced concrete slab in the shared space.
The library interior pad footings should be done later this week. Workers have started digging the elevator pit.
Electrical conduit and water pipes can now be seen emerging from the ground.
Underground plumbing is being installed. Digging continues for the installation of more underground plumbing and electrical service lines.